A multi-site manufacturerManaged Ignition
A multi-site manufacturer moved to a new cloud ERP across 18 factories. Plantformance rolled out on-premises Ignition so operators run fully local, whatever happens to the cloud or the network.
- 18 factories rolled out in 14 months
- 100% of operations run locally
Read the case study→NexinLifeMigration and carve-out
When two NexinLife factories were sold to a new group, Plantformance ran the carve-out end to end. Operations kept the same cloud ERP and changed hands with only an 8-hour transition period.
- 2 factories carved out
- 8 h transition period, no other impact on operations
Read the case study→An abrasives manufacturerMES and traceability
An abrasives manufacturer making expensive, long-lead parts went from paper tracking to a full MES. Complaint answers now take minutes, productivity rose 20%, and customer complaints fell 30%.
- 99% less time to answer a customer complaint
- +20% productivity
- 30% fewer customer complaints
Read the case study→A multi-site manufacturing groupIntegration and data
A manufacturing group running Ignition under strict security rules needed approval for every new connection at every plant. Plantformance built one reusable data layer, so a new interface now goes from request to 20 factories in 2 weeks.
- 2 weeks from interface request to rollout
- 20 factories per rollout
Read the case study→A multi-site manufacturing groupMigration and carve-out
A manufacturing group ran thousands of Ignition applications on 8.1.x across more than 100 factories. Plantformance automated the move to Ignition 8.3, reaching about 12 minutes per factory with a 96% success rate.
- 100+ factories migrated to Ignition 8.3
- 12 min to migrate one factory
- 96% migration success rate
Read the case study→A multi-site abrasives manufacturerIntegration and data
An abrasives manufacturer wanted local data from 31 factories in its Azure cloud without new security approvals per site. Plantformance built one central connection and an Ignition module that lets developers stream any tag with a click.
- 31 factories in scope
- 5 s default send interval
- 10k tags per aggregated batch
Read the case study→A multi-site manufacturing groupIntegration and data
A manufacturing group needed exact cloud copies of its local Ignition tables without touching edge performance. Plantformance built a change-capture pipeline, so turning on sync for a table now takes a 2-minute change request.
- 15 min change-check interval
- 1:50 typical compression ratio
- 2 min to build a sync change request
Read the case study→Saint-Gobain GlassIntegration and data
Saint-Gobain Glass built an edge management app on Ignition that needed heavy links to MicroStrategy, MS Planner and more. Plantformance built a central middleware layer, so every factory is covered by default with nothing to set up.
- 18 factories covered by default
- 5 interfaces per factory abstracted centrally
Read the case study→A European glass producerManaged Ignition
A glass producer wanted Ignition in a large factory running traditional SCADA. Plantformance shipped stock FactoryBrain servers within 24 hours, and Ignition was live for developers 5 days after the order.
- 5 days from order to Ignition live on site
- -97% versus usual project duration
- 24 h to ship the servers
Read the case study→Saint-GobainManaged Ignition
Saint-Gobain wanted Ignition across many sites without each factory building its own. Plantformance added a client standardization layer, a digital rollout method, and identical servers that are easy to maintain and update.
Read the case study→Saint-GobainSecurity and infrastructure
A penetration test exposed risks in the client-side authorization model of the legacy Vision module. Plantformance reviewed 3000+ applications, mitigated the attack chain, and added real-time monitoring, so Saint-Gobain could keep Vision running safely.
- 3000+ factory applications reviewed
Read the case study→A multi-site manufacturing groupSecurity and infrastructure
A manufacturing group asked Plantformance to install a centrally managed endpoint security agent on its Ignition servers. Plantformance proposed hardened Linux controls plus real-time event forwarding instead, rolled out to 180+ servers at no extra cost.
- 180+ servers rolled out the next day
Read the case study→A multi-site industrial manufacturerManaged Ignition
A manufacturer wanted to separate Ignition development from production across 90 factories. Plantformance turned the spare FactoryBrain node into an isolated development instance, so any site with a 2-server setup can add one with no change in operating costs.
- 90 factories previously shared 1 or 2 development servers
Read the case study→An abrasives manufacturerHMI
Ignition projects were stalling because operator PCs arrived months after the servers. Plantformance built FactoryClient, a purpose-built Ignition client with a 2 min setup assistant, cutting total cost of ownership by 80%.
- -80% total cost of ownership
- 3-6 months previous wait for operator clients
- 2 min configuration assistant at boot
Read the case study→An abrasives manufacturerHMI
Operator stations with touchscreens, scanners, and badge readers took too many parts and suppliers to deploy. Plantformance built FactoryTouch, an all-in-one terminal with 2 cables and a 5 min setup.
- -82% cables per operator station (11 to 2)
- -80% devices per operator position
- 5 min station setup
Read the case study→PlantformanceIgnition modules
Users with developer rights could make themselves Ignition gateway administrators. Plantformance replaced periodic script checks with the Security Auditor module, which detects escalation on the fly and responds automatically.
Read the case study→An abrasives manufacturerMES and traceability
An abrasives manufacturer had no real-time view of oven heating, soaking, and cool-down phases tied to work orders. Plantformance built an Ignition Vision application that detects each phase automatically and links it to the work order.
Read the case study→PlantformanceIgnition modules
Scripting to extend Ignition stopped scaling. Plantformance moved to building its own modules, launched 5 commercial Ignition modules with 6 more in the pipeline, and had developed 16 modules internally by the end of 2026.
- 16 Ignition modules developed internally
- 5 commercial Ignition modules
- 6 more modules in the pipeline
Read the case study→PlantformanceManaged Ignition
Configuring a fleet of 200+ Ignition servers one by one took too long and risked drift. Plantformance built an Ignition module that lets its orchestrator run changes on server groups in one click, cutting execution time by 99%.
- 99% less configuration execution time
- 1 min to configure 10 servers, down from 10 min each
- 200+ Ignition servers managed
Read the case study→PlantformanceManaged Ignition
Plantformance built a standardized FactoryBrain architecture, proactive monitoring and in-house automation so a compact engineering team can build, provision, develop and support more than 200 production Ignition servers end to end.
- 200+ production Ignition servers supported worldwide
- ~10 engineers running the full fleet
Read the case study→Saint-Gobain AbrasivesHMI
Plantformance built Skeleton, a standard Ignition Vision master template for Saint-Gobain Abrasives, so every new plant application ships with the same compliant interface and a ready-made two-way SAP ERP integration.
- 100% UI consistency across sites
Read the case study→A glass manufacturerMES and traceability
Plantformance replaced an aging machine monitoring tool on a critical glass line with an Ignition application that captures data at the right process moment, keeps full traceability and has run for years without modification.
- 7 to 8+ years in production without changes
- Zero application modifications required
Read the case study→PlantformanceSecurity and infrastructure
Plantformance re-engineered FactoryBrain from scratch with client input, shipping 16 field-driven improvements and scaling the second generation to 240+ servers worldwide with zero manufacturing issues.
- 240+ Gen 2 servers deployed worldwide
- 99.5% smooth global commissioning rate
- 5 min deployment per preconfigured unit
Read the case study→An abrasives manufacturerMES and traceability
An abrasives manufacturer replaced an unsupported Windows XP OEM application on high-speed lines with an Ignition MES that unifies ERP orders, machine data and item specs, with an estimated +30% performance and +10% quality gain.
- +30% estimated machine performance
- +10% estimated quality improvement
- 1 FTE saved per factory
Read the case study→Saint-Gobain AbrasivesMES and traceability
Plantformance moved a Saint-Gobain Abrasives workshop from paper, isolated PLCs and legacy SCADA to a paperless, SAP-driven Ignition MES, cutting WIP container lookups from hours to seconds. The template is now used across its plants globally.
- 100% paperless, SAP-driven workflow
- Up to 4 parallel batches queued
Read the case study→An abrasives manufacturerMES and traceability
An abrasives manufacturer rebuilt a sprawling, hardcoded MES into one data-driven engine for 14 machine types, so adding a machine or a site became a configuration task instead of a software project.
- 96% test scenarios resolved (320 of 333) in the first month
- 8 to 40 rollout-ready machines (of 75) in two weeks
- 14 machine types on one engine
Read the case study→Saint-Gobain GlassMES and traceability
Plantformance re-engineered Saint-Gobain Glass's laminated glass MES at its own expense, turning diverging plant versions into one global template with modular local layers that new lamination lines can follow.
- 480 h re-engineering invested by Plantformance
- ~70% common features before the rebuild
Read the case study→PlantformanceManaged Ignition
Plantformance built a predictive FactoryBrain monitoring platform that spots disk exhaustion, expiring certificates, privilege escalation and hardening drift early, across 3,000+ hosted Ignition applications, and fixes them before production is affected.
- 3,000+ hosted Ignition applications monitored
Read the case study→PlantformanceSecurity and infrastructure
Plantformance designs every customer-facing deployment security-first, with zero-trust networking, CISA Linux hardening, container isolation and multi-layer intrusion detection. Multiple independent penetration tests found zero critical issues.
Read the case study→PlantformanceSecurity and infrastructure
Plantformance designed the Isolated Client Module (ICM) architecture so large multi-site clients get physically separate hardware and a closed zero-trust jumpbox, with no direct laptop connections into factory OT networks.
- 100% hardware-level isolation between clients
Read the case study→PlantformanceSecurity and infrastructure
Plantformance built a multi-stage backup architecture for Ignition gateways: fast restores from high-speed storage, archive retention for up to a year, and monthly air-gapped tape kept in a bank vault.
Read the case study→PlantformanceManaged Ignition
Plantformance runs a 24/7 emergency workflow that combines FactoryBrain critical alarms and P1/P2 client tickets with on-call phone and SMS escalation, under a strict 15-minute acknowledgment SLA.
- 15 min acknowledgment SLA for P1/P2 issues
- 24/7/365 on-call engineer coverage
Read the case study→Saint-GobainManaged Ignition
For Saint-Gobain, Plantformance standardized FactoryBrain edge servers and centralized hosting with continuous telemetry, multi-tier backups and KPI tracking. The result: 3,000+ Ignition projects and multiple petabytes of data hosted over 8 years with zero data loss.
- 3,000+ Ignition projects hosted
- 8 yrs consecutive years of hosting
- Zero data loss
Read the case study→An abrasives manufacturerHMI
An abrasives manufacturer replaced office Windows PCs on the shop floor with Plantformance FactoryClient and FactoryTouch terminals. Fully managed updates now run with at most one minute of downtime, and devices last 7.5 to 9+ years.
- One minute maximum downtime per fleet-wide update
- 7.5-9+ yrs device service life
Read the case study→