Failed server replaced in 3 days during a global hardware shortage
failure ticket to on-site installation
When an out-of-warranty server node failed at a Saint-Gobain Life Sciences site during a global hardware shortage, Plantformance shipped a pre-stocked, provisioned and tested FactoryBrain node in 18h and completed the full replacement in 3 days, avoiding standard market lead times of 1 to 6 months.
Key results
- 3 days failure ticket to on-site installation
- 18 h incident to shipment
The problem
An out-of-warranty industrial server node failed at a Saint-Gobain Life Sciences site. The timing was bad. A severe global shortage of NVMe/SSD drives and enterprise server hardware was underway, and standard OEM replacement lead times usually ran from 1 to 6 months. Waiting that long would leave the site running without its server for months, with prices inflated by the same shortage.
What it looked like before
Without dedicated local stock, replacing an out-of-warranty server meant waiting 1 to 6 months for procurement and paying inflated market prices, with prolonged operational exposure.
How Plantformance solved it
Plantformance keeps critical FactoryBrain replacement nodes pre-stocked on the shelf for exactly this case. The team ran the whole response end to end: opening the ticket, investigating the root cause, issuing the quote, processing the order, provisioning and testing the node, shipping it and installing it on site. Because the hardware was already in stock, nothing waited on the market. The time from incident to shipment was 18h.
What changed
The client received a fully provisioned, tested replacement node installed on site, without waiting months for market supply.
Results
- Full replacement lifecycle completed in 3 days, from failure ticket to on-site installation
- Incident to shipment in 18h
- Avoided the 1 to 6 month standard market lead time
Plantformance products and services used
Frequently asked questions
How fast can Plantformance replace a failed industrial server?
For Saint-Gobain Life Sciences, Plantformance completed the full replacement lifecycle in 3 days, from failure ticket to on-site installation. The time from incident to shipment was 18h, because a FactoryBrain replacement node was already pre-stocked.
How does Plantformance avoid long hardware lead times during shortages?
Plantformance keeps critical FactoryBrain replacement nodes pre-stocked on the shelf. During a global NVMe/SSD and server hardware shortage, that let Plantformance skip the standard 1 to 6 month OEM lead time and inflated market prices.
Related Ignition case studies
- 3,000+ Ignition projects hosted for 8 years with zero data loss
- 15-minute acknowledgment for critical plant incidents, 24/7
- Predictive monitoring that catches Ignition failures before plants feel them
Planning a similar project? Talk to a Plantformance Ignition engineer or browse all 37 Ignition case studies.
Planning a similar Ignition project?
Tell us about your plants and your Ignition setup. A Plantformance engineer will show you how a project like this would work for you.