100+ factories upgraded to Ignition 8.3, down to 12 minutes per factory
factories migrated to Ignition 8.3
A multi-site manufacturing group ran thousands of Ignition applications on 8.1.x across 100+ factories. Plantformance built a daily readiness monitor and an automation tool that handled 99% of the migration to Ignition 8.3. By the end, one factory took about 12 minutes to migrate, with a 96% success rate.
Key results
- 100+ factories migrated to Ignition 8.3
- 12 min to migrate one factory
- 96% migration success rate
The problem
More than 100 factories ran Ignition 8.1.x, with thousands of Ignition applications ranging from monitoring to SCADA, including complex multi-site solutions. Then Ignition 8.3 came out. It brought the next-step architecture for the future, but it also made the upgrade harder. Every site had a different mix of applications, modules and interfaces, so a manual, site-by-site upgrade would have been slow and risky.
What it looked like before
A very complex landscape, with Ignition applications, modules, solutions, interfaces and devices that differed from site to site.
How Plantformance solved it
Plantformance built a purpose-built monitoring tool that checked every day how ready each Ignition server was for the move to 8.3. We prepared a summary per factory so the client had a precise to-do list for each site, and we sent a standard weekly report. Next, we built an automation tool that handled 99% of the migration. We then migrated sites one by one, starting with the easiest and moving to the most complex. By the end, migrating one factory took about 12 minutes, with a 96% success rate.
What changed
All factories were migrated to Ignition 8.3, except two special cases that need a local application rewrite.
Results
- The entire fleet of Ignition servers moved to the latest Ignition version
- About 12 minutes to migrate one factory by the end of the program, with a 96% success rate
- 99% of the migration automated
- The client uses the latest from Inductive Automation instead of staying tied to a legacy landscape for years
Plantformance products and services used
Frequently asked questions
How long does an Ignition 8.3 upgrade take per factory?
By the end of the program, Plantformance migrated one factory in about 12 minutes, with a 96% success rate. Sites were migrated one by one, starting with the easiest and moving to the most complex, using an automation tool that handled 99% of the migration.
How did Plantformance prepare each site for the upgrade?
Plantformance built a monitoring tool that checked every day how ready each Ignition server was for the move to 8.3. Each factory got a summary with a precise to-do list, and the client received a standard weekly report to track progress across the fleet.
Were all factories migrated to Ignition 8.3?
Yes, all factories were migrated to Ignition 8.3, except two special cases that need a local application rewrite. With the program Plantformance ran, the client now uses the latest from Inductive Automation instead of staying tied to a legacy landscape for years.
Related Ignition case studies
- New interfaces reach 20 factories in 2 weeks instead of years
- Streaming factory data to Azure in one click across 31 factories
- Full MES cuts customer complaint response time by 99%
Planning a similar project? Talk to a Plantformance Ignition engineer or browse all 37 Ignition case studies.
Planning a similar Ignition project?
Tell us about your plants and your Ignition setup. A Plantformance engineer will show you how a project like this would work for you.